Mammoet design input delivers maximum efficiency

As one of the largest crude oil processing locations in Germany, every hour of downtime at PCK Raffinerie GmbH’s (PCK) Schwedt refinery has a significant impact. So, when PCK needed two new cracking columns as part of a vital upgrade, they required a trusted partner who could transport and install the columns without any disruption to the surrounding live plant. Having supported PCK at its Schwedt refinery for nearly 20 years they approached Mammoet.
 
Early involvement, longstanding relationship and swift action in the face of adversity keep PCK oil refinery upgrade on schedule

Eight months earlier, Mammoet had begun a meticulous planning process in close collaboration with PCK. The columns would be delivered and installed in several sections. Being involved from an early stage meant that Mammoet was able to provide recommendations for the dimensions of the column sections during the design phase. This insight, together with the detailed knowledge of the site layout and the transport route, helped Mammoet find maximum efficiencies and deliver the project within the tight schedule.

According to Gernot Öder, Mammoet’s Manager Crane and Transport Projects: “Being able to advise on the dimensions of the column sections was invaluable to this project. Mammoet’s design insight at an early stage meant that we were able to work with the column sections as larger pieces. This was a time saving decision, as transporting the columns in larger pieces requires fewer journeys and means they can be assembled more efficiently onsite.”
 
Once Mammoet had successfully transported the reactors to the refinery site, the next stage was to complete the installation. However, on the day of the lifts, high winds meant that it was no longer safe to install the columns during the scheduled time slot. With every day being of paramount importance for the client, Mammoet completed the lifts during the night, when it was safe to do so, to ensure that the project was still delivered on time.
 
Gernot continues: “The wind was unexpected. Safety and efficiency are priorities, so to complete the lifts by the deadline we worked through the night. Our operators worked alternate shifts, completing the technically difficult lifts over the pipe racks using two CC 3800 crawler cranes.”
 
Being involved in the early phase, Mammoet utilized its knowledge, gained throughout a longstanding, 20-year working relationship to provide a solution that ensured the upgrade was completed safely and on time.

Sponsor : 

Other News Items

Digital Reliability: 24/7 Real-time Machinery Diagnostics

(WEBINAR) - Join Dynamics SPC where we will discuss our turnkey solution we call COMPACS. COMPACS monitors the health of your equipment in real-time. We’ve spent ...

25-02-2020

How Russia will ensure the growth of global methanol production by 2030

New and existing methanol projects in Russia and the CIS have become one of the topics in focus at the 6th Conference on Gas Monetisation, which will be held on April ...

23-01-2020

European refineries are the least prepared as IMO 2020 regulations loom large

European refineries expect the largest impact from new IMO 2020 regulations, yet just 23% of these refineries are focussing on operational improvements targeting higher ...

21-01-2020

RefComm® Galveston 2020 will be held 11-15 May

RefComm® Galveston 2020 will be held May 11 - 15, 2020 at the Moody Gardens Hotel and Conference Center in Galveston, TX. This marks the 22nd year for the conference, ...

16-01-2020

Alfa Laval wins energy efficiency order

Alfa Laval, a world leader in heat transfer, centrifugal separation and fluid handling – has won an order to supply Alfa Laval Packinox heat exchangers to a petrochemical ...

14-01-2020

Motor Oil Hellas select TechnipFMC for new naphtha complex in Greece

TechnipFMC has been awarded a significant Engineering, Procurement and Construction management (EPCm) services contract for the construction of a new naphtha complex ...

09-01-2020

Canada Kuwait Petrochemical Corporation select Fluor

Fluor Corporation announced today that Heartland Canada Partners (HCP), Fluor’s 50/50 partnership with Kiewit Construction Services ULC, was awarded a contract ...

09-01-2020

INEOS Styrolution invests in ABS world-scale plant in China

INEOS Styrolution, the global leader in styrenics, has announced today plans to build a world-scale ABS plant in Ningbo, China. The new production site will be adjacent ...

09-01-2020

Yokogawa releases Exaquantum R3.20 plant information management system

Yokogawa Electric Corporation announces the release of Exaquantum™ R3.20, an enhanced version of its plant information management system (PIMS) software package ...

07-01-2020

Sempra LNG and Aramco Services Company sign Port Arthur agreement

Sempra Energy and Saudi Aramco today announced their respective subsidiaries, Sempra LNG and Aramco Services Company, have signed an Interim Project Participation Agreement ...

06-01-2020