McDermott International Inc and its joint venture partner, Chiyoda International Corporation, a U.S. based wholly-owned subsidiary of Chiyoda Corporation, Japan, today announced that Train 2 of the Cameron project, located in Hackberry, La., has reached the final commissioning stage. This includes the introduction of pipeline feed gas into Train 2 of the liquefaction export facility, the precursor for the production of liquefied natural gas (LNG). This achievement is yet another significant milestone during 2019 and the first for Train 2.
McDermott announced introduction of feed gas to Train 1 on April 15, 2019, which was followed by first liquid on May 14 and first cargo from Train 1 on May 31. On August 19, Cameron LNG announced that Train 1 began commercial operation, following its substantial completion.
"Congratulations to the entire Cameron LNG project team who continues to make strides on this project and remains focused on providing stellar project delivery as we reach another notable milestone," said Mark Coscio, McDermott's Senior Vice President for North, Central and South America.
McDermott and Chiyoda have provided the engineering, procurement and construction for the Cameron LNG project since the project's initial award in 2014. The project includes three liquefaction trains with a projected export of 12 million tonnes per annum of LNG, or approximately 1.7 billion cubic feet per day.
McDermott announced introduction of feed gas to Train 1 on April 15, 2019, which was followed by first liquid on May 14 and first cargo from Train 1 on May 31. On August 19, Cameron LNG announced that Train 1 began commercial operation, following its substantial completion.
"Congratulations to the entire Cameron LNG project team who continues to make strides on this project and remains focused on providing stellar project delivery as we reach another notable milestone," said Mark Coscio, McDermott's Senior Vice President for North, Central and South America.
McDermott and Chiyoda have provided the engineering, procurement and construction for the Cameron LNG project since the project's initial award in 2014. The project includes three liquefaction trains with a projected export of 12 million tonnes per annum of LNG, or approximately 1.7 billion cubic feet per day.
- News Category :
- Company News
Honeywell technology to purify hydrogen for Zhejiang satellite C3 Oleflex™ facility
Honeywell today announced that Zhejiang Satellite Petrochemical Co., Ltd. is using a Honeywell UOP Polybed™ pressure swing adsorption (PSA) unit to supply high-purity ...
09-12-2019
Alfa Laval wins petrochemical order
Alfa Laval, a world leader in heat transfer, centrifugal separation and fluid handling – has won an order to supply large heat exchangers to a petrochemical plant ...
05-12-2019
LyondellBasell technology selected for polyolefin plant in Turkey
LyondellBasell today announced that Ceyhan Polipropilen Uretim A.Ş, a joint venture between Rönesans Holding and Sonatrach S.p.A., has selected LyondellBasell’s ...
03-12-2019
PKN ORLEN selects Fluor for its Olefins complex expansion project
Fluor Corporation announced today that it was awarded a services agreement by PKN ORLEN to provide project management contractor (PMC+) services for the expansion of ...
03-12-2019
Bunge and BP complete formation of BP Bunge Bioenergia JV
Bunge Limited and BP plc today announced that they have completed the formation of BP Bunge Bioenergia, the Brazilian bioenergy joint venture that combines their Brazilian ...
02-12-2019
McDermott and Chiyoda introduce feed gas to train 2 at Cameron LNG
McDermott International Inc and its joint venture partner, Chiyoda International Corporation, a U.S. based wholly-owned subsidiary of Chiyoda Corporation, Japan, today ...
02-12-2019
Neste Engineering Solutions updates its NAPCON product family
Neste Engineering Solutions has published a new 8.5 version of its NAPCON software. The renewed version has new software features in all NAPCON product categories: Train, ...
02-12-2019
R&D activities in refining technologies presented to the Gazprom Neft board
Gazprom Neft’s strategic objective to 2030 is to become the benchmark in safety, efficiency and technological advancement for other companies ...
29-11-2019
Rotork selected for strategic tank farm automation
Rotork has supplied over 100 actuators, including new actuated valve packages and actuators for the motorisation of existing gate and butterfly valves. In addition to ...
29-11-2019
PTT GC selects Avantium to perform independent catalyst testing evaluation
PTT Global Chemical has selected Avantium Catalysis to perform independent catalyst evaluation of naphtha reforming catalysts and support the catalyst selection for their ...
29-11-2019