Mammoet installs new FCC reactor head at Germany’s largest refinery
The Mineraloelraffinerie Oberrhein (MiRo) in Karlsruhe is preparing for its major scheduled turnaround in 2021. As part of this, the reactor head of the FCC plant is to be replaced and will be the largest single component lifted. The refinery turned to Mammoet for this project, thanks to its active participation in the project’s technical preparation, as part of an engineering study, and many years of trustful cooperation between the two organizations.
Before the project began, Mammoet’s engineering team was required to design and fabricate specialized transport saddles. These would allow passage through a narrow section of the route and ensured that the load could be set down and picked up again more easily when the transport configuration needed to be extended before entering the refinery.
At the end of October 2020, the 230t, 17m long and 9m diameter new reactor head reached the pioneer port in Karlsruhe by ship. Mammoet received the oversized heavy component by undertaking a ro-ro unloading operation with an SPMT combination of 2 x 10 axle lines.
" As a result of delays in shipping, the SPMT phase had to be postponed several times. However, since transport via public roads was only possible on certain days and an important access road to the refinery could only be closed on weekends, we coordinated the deployment so that the time slot could be kept exactly on a weekend. This reduced the impact on plant traffic significantly", explains Sören Müller, Project Manager at Mammoet.
The reactor head was then transported to the refinery via public roads for almost three kilometers. When leaving the port, the first challenge - a narrow tide gate — was overcome, as the custom-engineered transport saddles allowed safe passage through the gap.
Before entering the refinery, the transport configuration had to be extended to meet the maximum permissible axle loads of the bridges at the refinery. At a special conversion position, the load was set down hydraulically and the SPMT pair was extended to 2 x 24 axle lines.
In this way, the reactor head safely reached the pre-assembly position, where it was rotated by 90 degrees in a complex three-crane lift and set down on the pre-assembly frame in an upright position. Here, the heavy components are being prepared and temporarily stored, ready for the shutdown.
"With our integrated heavy-duty solution comprising ro-ro unloading, heavy transport via public roads and the three-crane lift, we were able to successfully support MiRo in reaching an important milestone in the modernization project", Müller continues.
News Category:
-
Beyond processbook & PI vision: Exploring today’s industrial analytics tools
(Webinar) - In the Manufacturing 4.0 era, industrial organizations have more data at their fingertips than ever, offering the promise of higher production rates, more ...
04-06-2024
-
Sasol provides state of the art catalysts to INERATEC for the production of sustainable e-fuels
The catalysts will be used, among others, in the first large-scale industrial Power-to-Liquid (PtL) plant that INERATEC is currently building in Frankfurt, Germany, which ...
24-04-2024
-
Baker Hughes to supply 17 centrifugal compressors to Saudi Master Gas System project
Baker Hughes, an energy technology company, announced Tuesday that it has received an order by Worley, for and on behalf of Aramco, to supply gas technology equipment ...
23-04-2024
-
SABIC Fujian Petrochemicals select Phenol yechnology from KBR
KBR announced today it has been awarded a contract by SABIC Fujian Petrochemicals to license KBR's market-leading phenol technology in China. Under the terms of the ...
22-04-2024
-
Lummus Expands R&D capabilities to enhance innovation and water and wastewater technologies
Lummus Technology, a global provider of process technologies and value-driven energy solutions, announced the opening of its cutting-edge research and development (R&D) ...
17-04-2024
-
Clariant launches new CATOFIN® 312 propane dehydrogenation catalyst
Clariant, a sustainability-focused specialty chemical company, today announced the launch of CATOFIN 312, its latest propane dehydrogenation catalyst. The new catalyst ...
16-04-2024
-
Yokogawa and GridBeyond conclude investment and strategic partnership agreements
Yokogawa Electric Corporation and energy IT solutions provider GridBeyond of Ireland announce that they have concluded a strategic partnership agreement. Furthermore, ...
16-04-2024
-
Heraeus Precious Metals launches Circlear
Heraeus Precious Metals, a globally leading company in the precious metals industry and one of the largest recyclers of precious metals, has introduced its new offering ...
16-04-2024
-
EMA and JERA to cooperate on LNG procurement and supply chains
The Energy Market Authority and JERA Co Inc, have signed a Memorandum of Understanding to cooperate on mutually beneficial areas in liquefied natural gas procurement ...
16-04-2024
-
Hexagon and Dragos unveil technical partnership to strengthen industrial cybersecurity
Hexagon’s Asset Lifecycle Intelligence division today announced a strategic partnership with Dragos, a global leader in cybersecurity for operational technology (OT). ...
16-04-2024