05-04-2012
Petronas rapid project progresses as scheduled
Petronas is pleased to inform that its proposed Refinery and Petrochemical Integrated Development (RAPID) project, to be located in Pengerang, Johor, is progressing as scheduled.
RAPID’s proposed refinery will have a capacity of 300,000 barrels per standard day and will supply feedstock for RAPID’s petrochemical complex as well as produce gasoline and diesel that meet European specifications. The RAPID project aims to capitalise on the growing need for specialty chemicals and to meet the demand for petroleum and commodity petrochemical products in the Asia Pacific region by 2016.
First announced by Prime Minister Dato’ Sri Mohd Najib Tun Abdul Razak on 13 May 2011, the project has achieved several important milestones in the past few months.
Following the announcement, a detailed feasibility study on the proposed project was undertaken, and was completed in October 2011. The project has since progressed to a Front-End Engineering Design (FEED) stage, while at the same time PETRONAS is finalising the selection of potential partners and licensors for the various facilities within the project. The site topographical survey and soil investigation work have been completed, while the Environmental Impact Assessment Study (EIA) is currently being performed.
Recently, PETRONAS signed a Heads of Agreement with BASF to jointly own, develop, construct and operate production facilities for specialty chemicals and plants for precursor materials within the RAPID complex. These world-scale facilities will be undertaken on a 40:60 basis.
Progress is also made in the various other technical and commercial aspects of the proposed project for PETRONAS to reach its final investment decision (FID) in the middle of 2013.
Except for pre-FID works, no other contract has been tendered out or awarded. PETRONAS will begin pre-qualification exercise for various tender packages for the project in stages, the earliest of which is expected to be held in the third quarter of this year.
On the human resource side, preparation is being made to ensure the availability of qualified and trained personnel to work at the various plants and facilities within the RAPID complex.
RAPID’s implementation has the potential of turning Southern Johor into a new refining and petrochemical centre in Malaysia, complementing the existing complexes in the country’s eastern corridors. It will also create multiple economic spin-offs and a new generation of oil and petrochemical professionals that will drive the development of this sector further, in line with the Government’s aspirations to turn Malaysia into a leading petroleum industry hub in the region.
News Category:
-
Maximizing Performance in Oil & Gas with Real-Time Analytics
(Webinar) - In an industry shaped by fluctuating market conditions and tight operational margins, oil & gas producers are increasingly relying on data-driven strategies ...
11-06-2025
-
Unlocking the potential of waste for advanced conversion pathways
(Webinar) - This session offers a detailed exploration of HTW® gasification technology, a proven solution for converting diverse feedstocks into clean syngas, which ...
05-06-2025
-
Zeopore fulfilling first customer orders
Zeopore, a leading innovator in zeolite enhancement technologies for high catalytic performance, proudly announces that its recently commissioned semi-industrial production ...
08-05-2025
-
Messe Frankfurt and DECHEMA team up for new ACHEMA Middle East
DECHEMA, which organises the ACHEMA, the leading trade show for the global process industry, launches ACHEMA Middle East in Saudi Arabia together with Messe Frankfurt. ...
06-05-2025
-
ABS and Akselos complete technical assessment for structural digital twin technology
ABS, a global leader in providing classification services for marine and offshore assets, with Akselos S.A., a global leader in structural performance management software; ...
06-05-2025
-
Sunoco LP and Parkland Corporation announced today that they have entered into a definitive agreement whereby Sunoco will acquire all outstanding shares of Parkland in ...
05-05-2025
-
Mission-critical flow control solutions from Valmet provides next level reliability
Industry-giant Valmet boasts an impressive array of topbrand automated on-off valves, control valves and controllers that are renowned for delivering longterm reliability ...
03-05-2025
-
MAIRE announces major contract wins
MAIRE announces that its subsidiaries TECNIMONT and KT-Kinetics Technology, also thanks to the technological and engineering services provided by NEXTCHEM, have been ...
29-04-2025
-
Borouge to boost production capacity
Borouge Plc, a leading petrochemicals company that provides innovative and differentiated polyolefins solutions, has today announced a series of strategic asset expansion ...
28-04-2025
-
Wanhua Chemical signs JV agreement with Petrochemical Industries Company
On April 25, Wanhua Chemical formally signed a joint venture agreement with Petrochemical Industries Company. Under the terms of the agreement, PIC invested USD ...
27-04-2025