Mammoet supports modernisation of MiRo refinery
The Mineraloelraffinerie Oberrhein (MiRo) in Karlsruhe is preparing for its major scheduled turnaround in 2021. As part of this, the reactor head of the FCC plant is to be replaced and will be the largest single component lifted. The refinery turned to Mammoet for this project, thanks to its active participation in the project’s technical preparation, as part of an engineering study, and many years of trustful cooperation between the two organizations.
Before the project began, Mammoet’s engineering team was required to design and fabricate specialized transport saddles. These would allow passage through a narrow section of the route and ensured that the load could be set down and picked up again more easily when the transport configuration needed to be extended before entering the refinery.
At the end of October 2020, the 230t, 17m long and 9m diameter new reactor head reached the pioneer port in Karlsruhe by ship. Mammoet received the oversized heavy component by undertaking a ro-ro unloading operation with an SPMT combination of 2 x 10 axle lines.
"As a result of delays in shipping, the SPMT phase had to be postponed several times. However, since transport via public roads was only possible on certain days and an important access road to the refinery could only be closed on weekends, we coordinated the deployment so that the time slot could be kept exactly on a weekend. This reduced the impact on plant traffic significantly.", explains Sören Müller, Project Manager at Mammoet.
The reactor head was then transported to the refinery via public roads for almost three kilometers. When leaving the port, the first challenge - a narrow tide gate — was overcome, as the custom-engineered transport saddles allowed safe passage through the gap.
Before entering the refinery, the transport configuration had to be extended to meet the maximum permissible axle loads of the bridges at the refinery. At a special conversion position, the load was set down hydraulically and the SPMT pair was extended to 2 x 24 axle lines.
In this way, the reactor head safely reached the pre-assembly position, where it was rotated by 90 degrees in a complex three-crane lift and set down on the pre-assembly frame in an upright position. Here, the heavy components are being prepared and temporarily stored, ready for the shutdown.
"With our integrated heavy-duty solution comprising ro-ro unloading, heavy transport via public roads and the three-crane lift, we were able to successfully support MiRo in reaching an important milestone in the modernization project.", Müller continues.
During the second phase of this project, Mammoet will replace the old reactor head with the new one using a crawler crane.
News Category:
-
Beyond processbook & PI vision: Exploring today’s industrial analytics tools
(Webinar) - In the Manufacturing 4.0 era, industrial organizations have more data at their fingertips than ever, offering the promise of higher production rates, more ...
04-06-2024
-
MOL inaugurates its polyol complex in Tiszaújváros
MOL's EUR 1.3 billion polyol complex in Tiszaújváros, boasting a capacity of around 200,000 tonnes of polyol per year, has been inaugurated. The ceremony, addressed ...
15-05-2024
-
NEXTCHEM completes the acquisition of GasConTec
Further to the announcement made on 4 March 2024, MAIRE announces that NEXTCHEM has finalized the acquisition of 100% of GasConTec GmbH, an innovative company specialized ...
15-05-2024
-
KBR awarded digital solutions contract by OCI
KBR announced today it has been awarded a contract by OCI Global to design and deploy its proprietary operator training simulator for OCI's 3,000 metric tonnes ...
13-05-2024
-
Worley awarded Bayou Bend CCS carbon capture and storage facility contract
We’ve been selected to design and evaluate CO2 gathering, handling and sequestration facilities located along the Gulf Coast in Southeast Texas. Bayou Bend ...
13-05-2024
-
Black & Veatch delivers feasibility study for Andes Energy LNG Terminal
Global liquefied natural gas (LNG) infrastructure solutions leader Black & Veatch has completed a feasibility study for the planned Andes Energy Terminal, LNG regasification ...
09-05-2024
-
Shell to sell interest in Singapore Energy and Chemicals Park to CAPGC
Shell Singapore Pte Ltd, a subsidiary of Shell plc, has reached an agreement to sell its Energy and Chemicals Park in Singapore to CAPGC Pte. Ltd., a joint venture company ...
08-05-2024
-
Integrated Global Services recognized for role in mega turnaround
Integrated Global Services has been recognized as a major contributor to the successful Ras Tanura Refinery 2024 Mega Turnaround and Inspection for Saudi Arabian Energy ...
08-05-2024
-
Ebara Elliott Energy to provide compressor for SAF project in Thailand
Ebara Elliott Energy, formerly Elliott Group, announces it has been contracted to provide a motor-driven recycle compressor with a variable frequency drive (VFD) for ...
07-05-2024
-
ETH Zurich select hte to provide high throughput test system designed for CO2 electroreduction
hte – the high throughput experimentation company was awarded a contract by the technical university ETH Zurich to provide a high throughput test system designed for ...
07-05-2024