Caustic tower revamp

A customer contacted Sulzer to increase capacity while improving the CO2 removal in the existing CO2 absorption column of their ethylene plant. This was the third revamp for this particular column and continued improvements can be hard to find. A proper caustic tower design requires a proper understanding of CO2 absorption with caustic.

CO2 + 2NaOH Na2CO3 + H2O

Sulzer replaced the conventional random packing with NeXRing and modified the operating parameters to match the packing performance. The result was a 20% increase in capacity and a vapor outlet CO2 concentration of less than 0.32 ppm, well exceeding expectations.

DOWNLOAD LITERATURE

View More

  • Safeguard packed column efficiency with proper liquid distribution

    Initial liquid distribution directly affects the efficiency of structured and random packing beds. As such, some form of flow test should be conducted to validate distributor performance prior to column startup. Steady state water flow testing is the most common method of testing distributors. It can ...

  • Separator technology reduces refinery operating costs and downtime

    A US refining company contacted us to discuss a separation problem in the feed to an alkylation process. Caustic entrainment from their selective hydrogenation unit was poisoning the hydrofluoric acid catalyst in the alkylation unit. The continuous phase feed to the alkylation unit consisted of ~180m3/hr ...

  • Tray designs for extreme fouling applications

    Today refiners experience a lot of problems with processing of opportunity or heavy crudes. Such crudes have very high sulfur content and require the addition of amine scavengers before desalting. These amines decompose in the heater and create ammonium chlorides in the presence of water in the top of ...

  • Anti-fouling trays maximize coker main fractionator profitability

    The Coker Main Fractionator is systematically subjected to harsh operating conditions that can lead to deteriorating efficiency and performance due to coking and fouling. Poor reliability results in loss of profitable coking margins for the refinery. The main fractionator vapor feed from the coke drum ...

  • Improve separation in your column by increasing the number of trays

    Refiners often face revamp challenges when trying to improve separation within an existing column. Improving diesel recovery from gas oil, splitting benzene precursors from naphtha reformer charge, or simply minimizing product overlaps after capacity creep can all be difficult when limited by a fi xed ...

  • Gain 5-10% efficiency with this simple 4-pass tray revamp

    The design of 4-pass trays can be complex. It not only requires a close evaluation of the mechanical design but also the process response to that design at various flow rates. The balancing of the fluid flows across the tray can have a substantial effect on the tray performance, namely efficiency. Many ...

  • Proper design of mass transfer internals in the FCC flue gas scrubber can help reduce PM emissions

    The EPA’s New Source Performance Standards (40 C.F.R. §60.100-1-0, subpart Ja) regulates refinery particulate emissions, including the discharge of catalyst fines from the FCCU flue gas scrubber stack. Because refiners have traditionally correlated particulate matter (PM) emissions with FCCU ...

  • Improve fouling resistance in your wastewater benzene stripper

    Benzene stripper columns, built so that refineries can meet the National Emissions Standards for Hazardous Air Pollutants (NESHAP), operate with several unique conditions – low vapor rates, high liquid loads, and a high tendency toward fouling make designing well-balanced, effective internals difficult. The ...

  • Important tray design features that improve column operating reliability

    How often does Maintenance personnel open a column during a shutdown and find tray panels fallen without any obvious damage? How about tray valves stuck in the bottoms pump suction? While the initial reaction may be to blame faulty installation where the hardware was not properly tightened, the answer ...

  • Green design practices: focus on efficiency

    Green design is more than recycling scrap materials or calculating carbon footprints. It minimizes negative environmental impact through skillful design and operating practices to produce efficient, better-functioning processes. Because green practices reduce resource requirements, in many cases, they ...